Frameworks · Managing change
Critical path analysis
A method of planning a project as a network of linked activities, to find the shortest time it can take, the activities that cannot slip, and the float on the rest.
Section 01: The framework at a glance
Text description
A network of six activities between six nodes, each node showing its number, earliest start time and latest finish time. Activity A, 3 weeks, runs from node 1 to node 2; Activity B, 4 weeks, runs from node 2 to node 3; Activity C, 2 weeks, runs from node 2 to node 4; Activity D, 5 weeks, runs from node 3 to node 5; Activity E, 3 weeks, runs from node 4 to node 5; Activity F, 2 weeks, runs from node 5 to node 6. The critical path is A, B, D, F, taking 14 weeks; its activities have no float. Activity C has a total float of 4 weeks and a free float of 0. Activity E has a total float of 4 weeks and a free float of 4.
Section 02: What it is, and what it is for
A project is drawn as a network: activities, each with a duration, run between numbered nodes, and an activity cannot start until those before it are finished. Each node records two times. The earliest start time is found by a forward pass, adding durations from the start and taking the largest total where paths meet. The latest finish time is found by a backward pass from the end, subtracting durations and taking the smallest result.
The critical path is the longest chain of dependent activities, and its length is the shortest possible duration of the project. Activities on it have no float, so any delay to them delays the whole project. Total float is how long an activity can be delayed without delaying the project; free float is how long it can be delayed without delaying the next activity. The guide expects students to complete and analyse a network and to calculate the floats, not to draw one from scratch.
What it is for
To schedule a project, find the activities that need the closest management, and see where resources can be moved without delaying completion. The toolkit lists it as an HL tool for units 4 and 5; its full guide is in preparation.
Section 03: How it is built
The parts of the framework, and what each one holds.
- Activities and dependencies
- Every task in the project, its estimated duration, and the tasks that must finish before it can start.
- The network
- Nodes joined by arrows for the activities, drawn from left to right so that every dependency is shown.
- Earliest start times
- Found by the forward pass: the earliest each activity can begin, taking the longest route into each node.
- Latest finish times
- Found by the backward pass from the end: the latest each activity can finish without delaying the project.
- The critical path
- The chain of activities with no total float. Its length is the shortest time in which the project can be finished.
- Total and free float
- Total float is how long an activity can slip without delaying the project; free float is how long it can slip without delaying the next activity.
Section 04: When to use it
The business situations it suits, and where another tool will serve better.
It suits
- Projects with many tasks that depend on each other and a fixed deadline, such as a refit, a product launch or the move to a new site.
- Deciding where to put extra people or money to shorten a project, which only helps on the critical path.
- Explaining to a client or a board what a delay to one task would do to the finish date.
Look elsewhere when
- Small projects with a handful of tasks, where a simple list or a Gantt chart is clearer.
- Work whose tasks and order are not known in advance, such as early research, where durations are little more than guesses.
Section 05: How to use it, step by step
A short method. The toolkit guide gives the full one, with the evidence each step needs.
- List the activities, their durations and which must finish before each can start.
- Complete the network: the forward pass gives the earliest start times at each node.
- Complete the backward pass from the final node to find the latest finish times.
- Find the critical path: the activities with no total float, which give the project's duration.
- Calculate total and free float for the other activities, and use them to plan resources and deal with delays.
Section 06: Applied: Fernwood Bistro plans its refit
Fernwood Bistro, a fictional restaurant, plans a refit with the six activities in the diagram above, in weeks: agree the design (A, 3), rebuild the kitchen (B, 4), order the furniture (C, 2), fit out the dining room (D, 5), install and test the furniture (E, 3) and final inspection and training (F, 2). B and C start after A; D follows B, E follows C, and F follows both D and E.
The longest path is A, B, D, F: 3 + 4 + 5 + 2 = 14 weeks. The other path, A, C, E, F, takes 10 weeks, so C and E each have a total float of 4 weeks. C's free float is 0, because E cannot start until it ends; E's free float is 4 weeks.
What it showed
The refit takes at least 14 weeks, and the kitchen and the dining room fit-out are the activities the manager must watch: a week's delay to either is a week's delay to reopening. The furniture work can slip by up to 4 weeks in total without delaying reopening, so a joiner can be shared with the kitchen work if needed.
Section 07: Reading the result
How to interpret what it shows, and what that does and does not justify deciding.
The critical path tells a manager where delay is not allowed. Any activity on it that runs late moves the finish date by the same amount; an activity with float can slip by up to its float without consequence.
Read the float as room to manage resources, not as spare time to waste: an activity with plenty of total float can lend people to the critical path. Watch the near-critical paths too. When a critical activity is shortened, another path may become critical, so the project gains less than the time saved.
What it can justify deciding
- Monitoring the activities on the critical path most closely, and starting them on time.
- Moving people or money from activities with float to critical ones, to protect or shorten the finish date.
- Telling stakeholders the earliest realistic finish date, and what a delay to a named activity would cost.
What it does not justify on its own
- Treating the finish date as certain: it is only as good as the duration estimates.
- Ignoring activities with float altogether; free float can be used up by one delay, and then they become critical.
Section 08: Strengths and limits
Why it helps
- It finds the minimum duration of a project and the activities that cannot slip.
- Float shows where there is flexibility to move people and equipment.
- It gives a basis for monitoring progress and judging the effect of delays.
Where it falls short
- Durations are estimates, and the critical path can change when they are wrong.
- Large networks are complex and need software to manage.
- It does not show the cost of activities or the people needed, unless these are added.
Section 09: Common mistakes
Errors often made with it, by students and by managers, and how to avoid each.
-
Mistake Taking the longest single activity to be the critical path.
Instead Add the durations along each route through the network; the critical path is the longest route, not the longest task.
-
Mistake Confusing total float with free float.
Instead Total float protects the project's end date; free float protects the start of the next activity. Calculate both from the earliest and latest times.
-
Mistake Drawing the network with dependencies that are convenient rather than real.
Instead List what must truly finish before each activity can start, and check the list with the people doing the work.
Section 10: Apply it
The application mode: the platform's tools that apply this framework, and a worksheet for your own case.
Frameworks structure judgement; they do not produce answers. Each one organizes evidence so that you can see it, test it and argue from it, and the decision, and the reasons for it, remain yours.
No interactive tool on the platform applies Critical path analysis in full yet, so the worksheet below is its application mode, with the tools that help with parts of it.
For part of it
- Case Room Halden Distribution: diagnose before you decide The case lab's planning stage asks you to order the activities of a change; it schedules them by critical path analysis against a deadline, and lets you test what a longer task does to the finish.
Your worksheet
Work through the framework part by part for a business you know, then say what the result does and does not justify.
Your worksheet could not be restored on this page; you can still fill it in and copy your work.
Kept on this device as you type, and nowhere else. Not saved without JavaScript: print the page or copy your answers before you leave.
The Framework Application Lab: choose a framework by the decision you face.
Section 11: Try it
The platform's own exercise. Write your answer, then open the guidance.
A school is staging a concert. Activities, in days: book the hall (A, 2); then rehearse (B, 10) and design and print posters (C, 4) can run at the same time; selling tickets (D, 6) can start once the posters are ready; the dress rehearsal (E, 1) needs the rehearsals finished, and the concert follows once both D and E are complete. Find the critical path, the minimum time to the concert, and the total float on C and D.
Kept on this device as you type, and nowhere else. Your answer is not saved without JavaScript; copy it before you leave.
The draft could not be restored on this page; you can still write and copy your answer.
Guidance: what a strong answer does
- Work out each path from start to finish and add its durations.
- The critical path is the longest path; its total is the minimum time.
- Total float is the difference between the critical path's length and the length of the longest path through the activity.
- Say which activity the organizers should watch most closely, and why.
Section 12: Related concepts
In the glossary
- Critical path analysis (CPA) A project-planning tool that shows a project's activities as a network, in the order they must happen, to find the shortest time in which the project can be completed and the activities that cannot be delayed without delaying it.
- Critical path The sequence of activities in a project that takes longest from start to finish, and so sets the shortest possible duration of the whole project.
- Total float The amount of time an activity can be delayed, or can overrun, without delaying the completion of the whole project.
- Free float The amount of time an activity can be delayed without delaying the earliest start of the activity that follows it.
- Gantt chart A bar chart that shows the tasks of a project against a time scale, with each bar showing when a task starts and how long it lasts.
Read with
- Gantt charts IB toolkit A chart of a project's tasks as bars against a timeline, showing when each starts and ends, which overlap, and the milestones along the way. Read the comparison: Critical path analysis and Gantt charts
- The RACI matrix Enrichment A grid of tasks against people that shows, for each task, who is responsible, who is accountable, who is consulted and who is informed. Compare side by side: Critical path analysis and The RACI matrix
- Decision trees IB toolkit A diagram of the options in a decision and their possible outcomes, with probabilities and payoffs, used to compare options by their expected value. Compare side by side: Critical path analysis and Decision trees
Compared with it: Gantt chart against critical path analysis . Or compare it with any other framework in the library.
Published works behind it
- James E. Kelley Jr and Morgan R. Walker (1959). Critical-Path Planning and Scheduling . Proceedings of the Eastern Joint Computer Conference.
Cited as bibliographic references in the platform's source register; the explanations on this page are the platform's own.
The explanation, method, example and exercise are the platform's own. Statements about the IB course cite the Business management guide; the business in the example is fictional.
Arjun Agrawal | The Business Brief, https://the-business-brief-dun.vercel.app/frameworks/critical-path-analysis/. Original teaching material, not an IB publication. The organizations in the teaching cases are fictional unless a case says otherwise.