Critical path analysis (CPA)
Also called CPA, Network analysis
Where you meet this term: IB DiplomaUndergraduateMBAProfessional
A project-planning tool that shows a project's activities as a network, in the order they must happen, to find the shortest time in which the project can be completed and the activities that cannot be delayed without delaying it.
In plain words
A way of planning a project by working out which tasks must happen in order, and which ones cannot be delayed without delaying the whole project.
In more depth
CPA models a project as a network of activities with durations and dependencies. A forward pass gives earliest start times, a backward pass latest finish times; activities with zero total float form the critical path, whose length is the minimum project duration. Total float is how far an activity can slip without delaying the project; free float is how far without delaying the next activity. The guide expects completion and analysis of a network, not drawing it.
In context
Each node records its number, the earliest start time (EST) of the activities that leave it and the latest finish time (LFT) of the activities that lead into it. From these the critical path and the float of every activity can be found, so managers know where to concentrate resources and which activities can wait. The guide expects HL students to complete and analyse a diagram they are given, identify the critical path and calculate free and total float, but not to draw the network themselves.
Example
A firm opening a new shop maps activities such as signing the lease, refitting, hiring staff and stocking shelves, and finds that the refit is on the critical path, so any delay to it delays the opening.
Common misconceptions
- Misconception
The critical path is the list of the most important tasks.
In factIt is the longest chain of dependent activities, those with no float; an important task can have plenty of float.
Frameworks, tools and diagrams
- Critical path analysis IB toolkit
- Gantt charts IB toolkit