A chart of a project's tasks as bars against a timeline, showing when each starts and ends, which overlap, and the milestones along the way.
Section 01: The framework at a glance
Text description
A Gantt chart for opening a fictional café over 12 weeks. Find and sign a site: weeks 1 to 3. Arrange finance: weeks 2 to 4. Fit out the café: weeks 5 to 9. Recruit staff: weeks 6 to 8. Train staff: weeks 9 to 10. Launch marketing: weeks 8 to 11. Opening day is a milestone in week 12. Overlapping bars run at the same time, and an arrow shows that fitting out cannot start until the finance is in place.
Section 02: What it is, and what it is for
A Gantt chart lists the tasks of a project down the side and time along the top. Each task is a bar from its start to its finish, so the chart shows at a glance the order of work, which tasks run at the same time, and the milestones, such as a launch date. Dependencies, where one task cannot start until another ends, can be shown with arrows, and progress can be shaded in as the project runs.
It is easy to read and good for communicating a schedule to a team. It shows dependencies less rigorously than a critical path network, and does not by itself reveal which tasks have float, so the two tools are often used together.
What it is for
To plan and track a project's timing, allocate people to tasks and communicate the schedule. The toolkit lists it as an HL tool for units 4 and 5; its full guide is in preparation.
Section 03: How it is built
The parts of the framework, and what each one holds.
- The task list
- Every task in the project, in the order they happen, with an estimated duration for each.
- The timeline
- A horizontal scale of days, weeks or months across the top of the chart.
- The bars
- One bar per task, starting when its dependencies allow and as long as its duration, so overlapping bars show tasks that run at the same time.
- Dependencies
- The tasks that must finish before another can start, shown by the bars' positions or by linking arrows.
- Milestones
- Key dates, such as an opening day or a sign-off, usually marked with a diamond.
- Progress
- How much of each task is done, shaded within its bar or marked against a line for today's date.
Section 04: When to use it
The business situations it suits, and where another tool will serve better.
It suits
- Communicating a project's timetable to a team, a client or a board who need to see at a glance what happens when.
- Tracking a project week by week, so that a task that slips is seen early.
- Planning the use of shared people or equipment, by seeing which tasks overlap.
Look elsewhere when
- Finding the critical path and the float of each task in a complex network, where critical path analysis is clearer.
- Work whose tasks are unknown or keep changing, where a fixed chart soon misleads.
Section 05: How to use it, step by step
A short method. The toolkit guide gives the full one, with the evidence each step needs.
- List the tasks and estimate the duration of each.
- Identify which tasks depend on others finishing first.
- Draw each task as a bar on the timeline, starting when its dependencies allow.
- Mark milestones and the project's end date.
- Track progress against the plan and adjust the bars when tasks slip.
Section 06: Applied: Juniper Café plans its opening
The owner of Juniper Café, a fictional business, plans the twelve weeks to opening day, as in the diagram above: find and sign a site (weeks 1 to 3), arrange finance (weeks 2 to 4), fit out the café (weeks 5 to 9), recruit staff (weeks 6 to 8), train staff (weeks 9 and 10) and run the launch marketing (weeks 8 to 11), with the opening in week 12.
What it showed
The chart shows that training cannot start until recruitment ends in week 8, and that the café cannot open until the trained staff are in place, so a delay of two weeks in hiring would leave almost no margin before opening day. The owner starts advertising the jobs a week earlier to build one in.
Section 07: Reading the result
How to interpret what it shows, and what that does and does not justify deciding.
Read the chart for its pinch points: places where several tasks overlap and compete for the same people, and chains of dependent tasks with no gap between them, where any delay passes straight through to the finish.
Compare the plan with progress regularly. A bar that is behind today's line is a problem only if a later task depends on it and has no room to absorb the delay, so check the dependency before reacting.
What it can justify deciding
- Starting early tasks sooner, or adding resources to a chain of dependent tasks, to build in a margin before a fixed date.
- Re-planning the bars when a task slips, and telling the people whose tasks depend on it.
What it does not justify on its own
- Concluding that tasks without visible dependencies can slip freely; the chart does not calculate float.
- Treating the end date as certain while the durations are estimates.
Section 08: Strengths and limits
Why it helps
- Easy to read, so everyone can see what happens when.
- Good for allocating people and spotting overlaps and clashes.
- Progress can be tracked against the plan visually.
Where it falls short
- Dependencies are harder to read than on a network diagram, especially in large projects.
- It does not by itself identify the critical path or the float on each task.
- Estimates of duration are uncertain, so the chart needs updating.
Section 09: Common mistakes
Errors often made with it, by students and by managers, and how to avoid each.
-
Mistake Drawing bars without showing which tasks depend on which.
Instead Mark the dependencies, so that the effect of a delay can be traced.
-
Mistake Making the chart once and never updating it.
Instead Record progress against the plan regularly and move the bars when tasks slip.
-
Mistake Treating the Gantt chart as a substitute for critical path analysis in a complex project.
Instead Use critical path analysis to find the critical path and float, and the Gantt chart to communicate and track the plan.
Section 10: Apply it
The application mode: the platform's tools that apply this framework, and a worksheet for your own case.
Frameworks structure judgement; they do not produce answers. Each one organizes evidence so that you can see it, test it and argue from it, and the decision, and the reasons for it, remain yours.
No interactive tool on the platform applies Gantt charts in full yet, so the worksheet below is its application mode, with the tools that help with parts of it.
For part of it
- Market Studio Marketing campaign planner Plan a campaign's channels and tasks week by week; the timeline is drawn as a Gantt chart, with checks on spending and on items outside the campaign.
- Case Room Halden Distribution: diagnose before you decide Schedule a change plan against a client's deadline in the case lab's planning stage, and see which activities have no room to slip.
Your worksheet
Work through the framework part by part for a business you know, then say what the result does and does not justify.
Your worksheet could not be restored on this page; you can still fill it in and copy your work.
Kept on this device as you type, and nowhere else. Not saved without JavaScript: print the page or copy your answers before you leave.
The Framework Application Lab: choose a framework by the decision you face.
Section 11: Try it
The platform's own exercise. Write your answer, then open the guidance.
Plan a school charity fair with six tasks, such as booking the hall, recruiting volunteers and advertising. Draw a Gantt chart over six weeks, show one dependency and one milestone, and explain which task would most delay the fair if it ran late.
Kept on this device as you type, and nowhere else. Your answer is not saved without JavaScript; copy it before you leave.
The draft could not be restored on this page; you can still write and copy your answer.
Guidance: what a strong answer does
- Give each task a realistic duration and a reason for its start date.
- Show at least one task that cannot start until another ends.
- Mark the fair itself as the milestone.
- Explain the delay using the dependencies, which is where critical path analysis adds detail.
Section 12: Related concepts
In the glossary
- Gantt chart A bar chart that shows the tasks of a project against a time scale, with each bar showing when a task starts and how long it lasts.
- Critical path analysis (CPA) A project-planning tool that shows a project's activities as a network, in the order they must happen, to find the shortest time in which the project can be completed and the activities that cannot be delayed without delaying it.
- Lead time The time between placing an order with a supplier and receiving the goods, ready to use.
Read with
- Critical path analysis IB toolkit A method of planning a project as a network of linked activities, to find the shortest time it can take, the activities that cannot slip, and the float on the rest. Read the comparison: Gantt charts and Critical path analysis
- The RACI matrix Enrichment A grid of tasks against people that shows, for each task, who is responsible, who is accountable, who is consulted and who is informed. Compare side by side: Gantt charts and The RACI matrix
- Lewin's change model Enrichment A three-stage model of change: unfreeze the current state, move to the new one, then refreeze so that the new way becomes stable. Compare side by side: Gantt charts and Lewin's change model
- The business plan IB toolkit A document that sets out what a new business or project will do, for whom, how it will operate and what it will cost and earn, to test an idea and win support for it. Compare side by side: Gantt charts and The business plan
Compared with it: Gantt chart against critical path analysis . Or compare it with any other framework in the library.
The explanation, method, example and exercise are the platform's own. Statements about the IB course cite the Business management guide; the business in the example is fictional.