Critical path
Where you meet this term: IB Diploma
The sequence of activities in a project that takes longest from start to finish, and so sets the shortest possible duration of the whole project.
In context
Activities on the critical path have zero total float: if any of them is delayed, the whole project is delayed. Managers watch critical activities closely and may move resources to them from activities that have float. A project can have more than one critical path, and the critical path can change if another activity overruns by more than its float.
Example
If activities A, C and F, taking 4, 6 and 5 days, must follow one another and every other route through the network is shorter, then A, C and F form the critical path and the project takes at least 15 days.