Case Room · Case lab
Diagnose before you decide
Five stages, one case. Find the real problem behind the symptoms, weigh the evidence for each cause, choose a strategy that acts on the strongest, plan it against the client's deadline, and judge the results when they come in. Each stage opens when the one before is done.
Interaction
Halden Distribution: problem, cause, strategy, implementation, evaluation
The lab could not start. Every stage is open below, and each answer can be opened under its question.
You are advising Amara Osei, Halden's new site manager, at the end of July, once her staff survey is in.
Since a warehouse management system arrived last December, on-time dispatch has fallen from 98.1% to 91.4%, picking errors have more than doubled and over half of the night shift has left within the year. Lumen Home, a third of the warehouse's work, wants dispatch above 97% by the first week of November. Before Amara chooses how to lead, she wants the problem diagnosed. Work through the five stages in order; each one starts from the last.
Stage 1 of 5.
The evidence 6 exhibits from the Halden Distribution case file. Fictional; simulated data.
The full case, with its narrative and stakeholders: Halden Distribution.
Site performance over the last year
Source: Simulated data| Month | On-time dispatch (%) | Picking errors per 1,000 orders | Absence rate (%) |
|---|---|---|---|
| August 2025 | 98.1 | 2.1 | 3.1 |
| October 2025 | 97.6 | 2.3 | 3.4 |
| December 2025 | 96.0 | 3.4 | 4.2 |
| February 2026 | 94.2 | 4.0 | 4.9 |
| April 2026 | 92.7 | 4.6 | 5.3 |
| June 2026 | 91.4 | 5.2 | 5.8 |
The warehouse management system went live in December 2025.
People, by shift, over the last twelve months
Source: Simulated data| Measure | Day shift | Night shift | Whole site |
|---|---|---|---|
| Employees now | 82 | 58 | 140 |
| Average number of employees in the year | 81 | 54 | 135 |
| Employees who left in the year | 18 | 28 | 46 |
| Labour turnover (%) | 22.2 | 51.9 | 34.1 |
| Average length of service (years) | 7.4 | 2.9 | 5.5 |
| Team leaders' average experience as team leaders (years) | 9.1 | 0.6 | |
| Training on the new system (hours per person) | 6 | 2 |
Labour turnover is the number of employees who left divided by the average number of employees, multiplied by 100. Two years ago it was 18.9% for the whole site.
Staff survey, July 2026 (112 of 140 responded)
Source: Simulated data| Statement | Day shift agreeing (%) | Night shift agreeing (%) |
|---|---|---|
| I know what is expected of me | 81 | 54 |
| I am consulted about changes that affect my work | 38 | 21 |
| I have had the training I need to use the new system | 72 | 33 |
| My team leader helps me solve problems | 74 | 48 |
| I would recommend Halden as a place to work | 58 | 29 |
66 day-shift and 46 night-shift employees responded. Across both shifts, the average share agreeing with the five statements is 53%, the engagement score used in the Decision Room.
The client's deadline
Source: Simulated dataOur customers were promised next-day delivery. Since the spring, nearly one order in eleven from your site has missed its truck. We need on-time dispatch back above 97% by the first week of November, when our peak season starts. If it is not, we will move our contract when the current year ends.
Why night-shift leavers left (exit interviews with 24 of the 28)
Source: Simulated data- Nobody explained the new scanners properly
- 11
- Targets changed without warning
- 7
- Better pay elsewhere
- 4
- The shift pattern
- 2
How the previous manager led
Source: Simulated dataGraham knew everyone's kids' names. He decided everything himself, but you always felt looked after. When the scanners came in, he just told us they were coming.
- 01 Problem
What is the problem?
DoneFinish stage 00 first. Each stage builds on the one before.
A diagnosis starts by separating what can be seen (symptoms) from what has to be solved (the problem) and from what will happen if it is not (consequences). A good problem statement is specific, rests on evidence and does not contain its own solution.
Read: Exhibit 1 Exhibit 2 Exhibit 4
This exercise could not start. Each item's answer is in the "Answer and explanation" section below it.
Is each of these a symptom, the problem, or a consequence?
-
On-time dispatch has fallen from 98.1% to 91.4% since the new system went live.
Answer and explanation
Answer: Symptom.
A measure of what is going wrong, not the reason. Fixing the number directly, by holding trucks back for example, would leave the cause in place.
Evidence: Exhibit 1.
-
Picking errors have risen from 2.1 to 5.2 per 1,000 orders.
Answer and explanation
Answer: Symptom.
Another measure of the same trouble, and a clue to it, because errors are what an untrained picker makes.
Evidence: Exhibit 1.
-
Over half of the night shift left within the year (labour turnover of 51.9%).
Answer and explanation
Answer: Symptom.
A symptom, though one that feeds the problem: each leaver is replaced by someone even less familiar with the system. Arguing that it is part of the problem is reasonable; it is still a result of something else.
Evidence: Exhibit 2.
-
The night shift was given the new system with a third of the day shift's training and almost no say, and cannot yet work with it.
Answer and explanation
Answer: Problem.
This is what has to be solved. It explains the symptoms, it is specific about who and what, and it does not yet say what to do.
Evidence: Exhibit 2.
-
Lumen Home will move its contract if dispatch is not above 97% by November.
Answer and explanation
Answer: Consequence.
What happens if the problem is not solved. It sets the deadline and the stakes, but it is not the problem itself.
Evidence: Exhibit 4.
This exercise could not start. Each item's answer is in the "Answer and explanation" section below it.
-
Which is the best statement of the problem?
Answer and explanation
Answer: The night shift cannot yet work with the new system.
The first option is the objective, the result the problem is preventing: useful, but it says nothing about why. Nothing in the exhibits suggests a lack of effort, and the survey points elsewhere. The scanners are the same on both shifts, and the day shift, trained for six hours, adapted. The third statement names who, what and the evidence, and leaves the cure open.
Who, what, since when, and the evidence. No solution yet. Kept on this device for your memo.Check every answer in this stage to continue. -
- 02 Cause
What is causing it?
DoneFinish stage 01 first. Each stage builds on the one before.
Several causes can be suggested for any problem. Weigh each by its evidence before choosing what to act on. A cause with strong evidence and a large effect is worth more than three with a little of each.
Read: Exhibit 2 Exhibit 3 Exhibit 5 Exhibit 6
This exercise could not start. Each item's answer is in the "Answer and explanation" section below it.
How strong is the evidence for each possible cause?
-
Too little training on the new system
Answer and explanation
Answer: Strong evidence.
Two hours of training on the night shift against six on the day shift (Exhibit 2); 33% of the night shift say they have had the training they need, against 72% of the day shift (Exhibit 3); and 11 of the 24 leavers interviewed said nobody explained the scanners properly (Exhibit 5).
Evidence: Exhibit 2, Exhibit 3, Exhibit 5.
-
Changes made without consulting the people who do the work
Answer and explanation
Answer: Strong evidence.
21% of the night shift feel consulted about changes that affect them (38% of the day shift); 7 of 24 leavers left because targets changed without warning; and the founder "just told us" the scanners were coming (Exhibits 3, 5 and 6).
Evidence: Exhibit 3, Exhibit 5, Exhibit 6.
-
Inexperienced night-shift team leaders
Answer and explanation
Answer: Some evidence.
The night team leaders have 0.6 years' experience in the role against 9.1 on days, and 48% of the night shift say their team leader helps them solve problems (74% on days). It is a contributing cause: it explains why nobody filled the training gap on the floor.
Evidence: Exhibit 2, Exhibit 3.
-
Pay is lower than elsewhere
Answer and explanation
Answer: Some evidence.
Four of the 24 leavers gave better pay elsewhere as their main reason. That is real but minor, one leaver in six, and it says nothing about errors or dispatch.
Evidence: Exhibit 5.
-
The scanners or the software are faulty
Answer and explanation
Answer: No evidence.
Nothing in the exhibits points to a fault, and the day shift adapted to the same system after six hours' training.
Evidence: Exhibit 2, Exhibit 3.
-
The night shift does not care about the work
Answer and explanation
Answer: No evidence.
The exhibits point the other way. The night shift's answers and the exit interviews are about training and being heard, not about effort.
Evidence: Exhibit 3, Exhibit 5.
Name the evidence, and say how much of the problem it explains. Kept on this device for your memo.Check every answer in this stage to continue. -
- 03 Strategy
What should Halden do?
DoneFinish stage 02 first. Each stage builds on the one before.
A strategy should act on the strongest causes, fit the time and money available, and not create a new problem. Judge each option against all three.
Read: Exhibit 2 Exhibit 4 Exhibit 5
This exercise could not start. Each item's answer is in the "Answer and explanation" section below it.
-
Which strategy should Amara recommend to the owners?
Answer and explanation
Answer: Retrain and redesign with the night shift.
It acts on both strong causes and the contributing one, and it can be done before November. The bonus would cost about £58,000 for the 58 night-shift employees and addresses a cause behind 4 of 24 departures, leaving the skill gap where it is. Replacing a system there is no evidence against would take longer than the three months left and repeat the kind of change that caused the problem. Targets and warnings bring clear standards fast, which is why the option is partly right, but they treat a skill problem as an effort problem: in the Decision Room, that route raises turnover and misses the deadline.
What must be true for it to work? Kept on this device for your memo.Check every answer in this stage to continue. -
- 04 Implementation
Plan it in the time available
DoneFinish stage 03 first. Each stage builds on the one before.
A plan is a sequence: some activities cannot start until others finish. The longest chain of dependent activities sets the earliest finish. The plan starts in the first week of August; Lumen Home's deadline, the first week of November, is 14 weeks away.
This exercise could not start. Each item's answer is in the "Answer and explanation" section below it.
Must each of these finish before the pilot in two zones can start?
-
Listening sessions with the night shift
Answer and explanation
Answer: Must finish first.
The redesign is built on what the night shift says, and the retraining on the redesign, so listening comes first in the chain that leads to the pilot.
-
Coaching for the two night team leaders
Answer and explanation
Answer: Need not.
Coaching runs alongside and must be finished before the full roll-out, when the team leaders take over. The pilot can start without it.
-
Redesigning the night pick routes with a group of pickers
Answer and explanation
Answer: Must finish first.
The pilot tests the redesigned routes, so they must exist first.
-
Retraining the night shift on the scanners and the new routes
Answer and explanation
Answer: Must finish first.
Piloting with untrained pickers would repeat the original mistake.
-
Day-shift buddies for night pickers
Answer and explanation
Answer: Need not.
Buddying follows the retraining and runs alongside the pilot and roll-out; it must be finished only before the readiness check.
The plan, week by week
The plan takes 13 weeks: 1 week inside the deadline.
Plan Black bars are the critical path; blue bars have float, shown as a dotted line to the latest finish. The dashed red line is the deadline. This is a Gantt chart: Gantt charts and critical path analysis, with its float, are HL toolkit content (guide, p. 14). The plan as a table
Activity Weeks Starts in week Ends with week Total float Path Listen to the night shift 1 1 1 0 Critical Coach the night team leaders 6 1 6 3 Has float Redesign night pick routes 3 2 4 0 Critical Retrain the night shift 3 5 7 0 Critical Day-shift buddies 4 8 11 1 Has float Pilot in two zones 2 8 9 0 Critical Roll out and review weekly 3 10 12 0 Critical Peak readiness check 1 13 13 0 Critical Which activity has no room to slip? Kept on this device for your memo.Check every answer in this stage to continue. -
- 05 Evaluation
Is it working, and how would you know?
DoneFinish stage 04 first. Each stage builds on the one before.
Decide how success will be measured before the results arrive, then judge the results against the objective, the trend and the time left, not one number on one day.
This exercise could not start. Each item's answer is in the "Answer and explanation" section below it.
Is each of these a good measure of whether the plan is working?
-
On-time dispatch each week, by shift
Answer and explanation
Answer: Good measure.
The client's own test, measured often enough to steer by, and by shift so that the night shift's progress is visible.
Evidence: Exhibit 1, Exhibit 4.
-
Picking errors per 1,000 orders, by shift
Answer and explanation
Answer: Good measure.
Errors are the most direct sign of whether pickers can use the system, and they move before dispatch does.
Evidence: Exhibit 1.
-
Night-shift leavers, counted over each rolling three months
Answer and explanation
Answer: Good measure.
It shows whether the shift is stabilizing, sooner than an annual labour turnover figure would.
-
Hours of training delivered
Answer and explanation
Answer: Partly.
It shows the plan is being carried out, not that it works. Useful as a check on progress, poor as a measure of success.
-
Halden's profit for the year
Answer and explanation
Answer: Poor measure.
Too late and too broad: it will not be known until after the deadline, and it depends on far more than the night shift.
Check-inSimulated check-in, week 10 of the plan
Source: Simulated dataMeasure Before the plan Week 10 On-time dispatch (%) 91.4 95.6 Picking errors per 1,000 orders 5.2 3.3 Night-shift leavers in the last ten weeks 3 Night shift agreeing they have had the training they need (%) 33 71 Night shift agreeing they are consulted about changes (%) 21 58 Simulated for this lab, to practise judging results. Week 10 is four weeks before Lumen Home's deadline. Three leavers in ten weeks from about 56 night-shift employees is an annual rate of about 28%, against 51.9% a year ago. This exercise could not start. Each item's answer is in the "Answer and explanation" section below it.
-
What is the most defensible judgement at week 10?
Answer and explanation
Answer: It is working; keep going and watch the trend.
Dispatch has risen 4.2 points in ten weeks, about 0.42 a week. At that pace it would pass 97% in three to four more weeks, just inside the deadline, though improvements often slow as the easy gains are taken, so the weekly figure matters more than the projection. Errors have fallen and the night shift feels trained and heard, so the causes are being treated. Calling it a success is premature, because the client's test is dispatch; switching to warnings would put at risk the trust the plan has built.
Go back down the chain. Which cause might not have been treated? Kept on this device for your memo.Check every answer in this stage to continue. -
To the owners of Halden Distribution
Your sentences from each stage, beside the platform's reasoning. Compare them, then improve yours.
- Problem Yours
Not written yet.
The platform's reasoningSince the system went live in December, the night shift, trained for two hours against the day shift's six and consulted less, has not been able to work with it: dispatch and accuracy have fallen and over half the shift has left. Lumen Home's deadline makes this urgent, but it is the consequence, not the problem.
- Cause Yours
Not written yet.
The platform's reasoningTwo causes have strong evidence and explain most of the problem: too little training on the new system and changes made without the night shift's involvement. Inexperienced team leaders made both worse. Pay matters to a few leavers; nothing suggests faulty scanners or a lack of effort.
- Strategy Yours
Not written yet.
The platform's reasoningRetrain the night shift on the system and redesign night picking with the people who do it, supported by day-shift buddies and coaching for the night team leaders. It acts on the causes with the strongest evidence, costs far less than a bonus or a new system, and fits the three months left, provided the training is finished early enough to leave time for a pilot.
- Implementation Yours
Not written yet.
The platform's reasoningListening, redesign, retraining, the pilot, the roll-out and the readiness check form the critical path: thirteen weeks, one week inside the deadline. Coaching and buddying have float. The risk is retraining: every extra week it takes moves the finish by a week, so at four weeks the plan only just meets the deadline and at five it misses it. Train in small groups from the first week the routes are ready, and keep the coaching going alongside.
- Evaluation Yours
Not written yet.
The platform's reasoningAt week 10 the plan is working but has not yet succeeded. Dispatch is 95.6% and rising by about 0.4 points a week, errors are down by more than a third, and the night shift reports the training and consultation it lacked. Keep going, review weekly by shift, and if dispatch stalls, go back to the causes: check the team leaders' coaching and whether the redesigned routes are being used.
Arjun Agrawal | The Business Brief, https://the-business-brief-dun.vercel.app/case-room/halden-diagnosis/. Original teaching material, not an IB publication. The organizations in the teaching cases are fictional unless a case says otherwise.