Free float

Where you meet this term: IB Diploma

The amount of time an activity can be delayed without delaying the earliest start of the activity that follows it.

In plain words

How long an activity can be delayed without delaying the earliest start of the activity after it.

In more depth

Free float = earliest start time of the next activity − duration − earliest start time of this activity. It is never more than total float. Because using it affects no other activity, it is the float a manager can use first.

Formula

Free float = earliest start time of the next activity − duration − earliest start time of this activity

See it worked in the toolkit guide to critical path analysis

In context

Free float can never be larger than total float. It matters when the next activity uses people or equipment booked for a particular day: using up free float disturbs no one else's schedule, while using up the rest of the total float pushes later activities back. Critical activities have zero free float as well as zero total float.

Example

An activity that can start on day 6 and lasts 3 days, followed by an activity that cannot start before day 10, has a free float of 10 − 3 − 6 = 1 day.

Common misconceptions

  • Misconception

    Free float and total float are the same thing.

    In fact

    Total float is the delay the whole project can absorb; free float is the delay the next activity can absorb, and it can be smaller.