Measure or calculation HL only
Free float
Where you meet this term: IB Diploma
The amount of time an activity can be delayed without delaying the earliest start of the activity that follows it.
In plain words
How long an activity can be delayed without delaying the earliest start of the activity after it.
In more depth
Free float = earliest start time of the next activity − duration − earliest start time of this activity. It is never more than total float. Because using it affects no other activity, it is the float a manager can use first.
Formula
Free float = earliest start time of the next activity − duration − earliest start time of this activity
See it worked in the toolkit guide to critical path analysis
In context
Free float can never be larger than total float. It matters when the next activity uses people or equipment booked for a particular day: using up free float disturbs no one else's schedule, while using up the rest of the total float pushes later activities back. Critical activities have zero free float as well as zero total float.
Example
An activity that can start on day 6 and lasts 3 days, followed by an activity that cannot start before day 10, has a free float of 10 − 3 − 6 = 1 day.
Common misconceptions
- Misconception
Free float and total float are the same thing.
In factTotal float is the delay the whole project can absorb; free float is the delay the next activity can absorb, and it can be smaller.
Frameworks, tools and diagrams
- Critical path analysis IB toolkit
Related terms
Suggested next
- Gantt chart Linked through Critical path analysis (CPA)
- Free cash flow (FCF) Beyond IB A related name