Total float
Where you meet this term: IB Diploma
The amount of time an activity can be delayed, or can overrun, without delaying the completion of the whole project.
In plain words
How long an activity in a project can be delayed without delaying the whole project.
In more depth
Total float = latest finish time − duration − earliest start time. Activities on the critical path have no total float, so any delay to them delays completion. Total float can be shared by a chain of activities, so using it up on one can leave none for the activities after it.
Formula
Total float = latest finish time − duration − earliest start time
See it worked in the toolkit guide to critical path analysis
In context
It is calculated from the activity's duration, the earliest start time at its start node and the latest finish time at its end node. Activities with zero total float are critical. Total float can be shared along a chain of activities, so using it up on one activity can leave less for those after it.
Example
An activity that can start on day 6 at the earliest, lasts 3 days and must finish by day 12 has a total float of 12 − 3 − 6 = 3 days.
Common misconceptions
- Misconception
An activity with total float can be delayed by that much without any effect.
In factThe project still finishes on time, but the delay may use up float that the later activities in the same chain were relying on.
Frameworks, tools and diagrams
- Critical path analysis IB toolkit
Related terms
Suggested next
- Total contribution A related name
- Total addressable market (TAM) Beyond IB A related name
- Gantt chart Linked through Critical path analysis (CPA)
- Total cost A related name
- Total quality management (TQM) A related name
- Total revenue A related name