Total float

Where you meet this term: IB Diploma

The amount of time an activity can be delayed, or can overrun, without delaying the completion of the whole project.

In plain words

How long an activity in a project can be delayed without delaying the whole project.

In more depth

Total float = latest finish time − duration − earliest start time. Activities on the critical path have no total float, so any delay to them delays completion. Total float can be shared by a chain of activities, so using it up on one can leave none for the activities after it.

Formula

Total float = latest finish time − duration − earliest start time

See it worked in the toolkit guide to critical path analysis

In context

It is calculated from the activity's duration, the earliest start time at its start node and the latest finish time at its end node. Activities with zero total float are critical. Total float can be shared along a chain of activities, so using it up on one activity can leave less for those after it.

Example

An activity that can start on day 6 at the earliest, lasts 3 days and must finish by day 12 has a total float of 12 − 3 − 6 = 3 days.

Common misconceptions

  • Misconception

    An activity with total float can be delayed by that much without any effect.

    In fact

    The project still finishes on time, but the delay may use up float that the later activities in the same chain were relying on.