Gantt chart

A bar chart that shows the tasks of a project against time, used to plan and monitor progress.

HL only Verification: Verified In the IB toolkit Updated 3 November 2026

Section 01: What it is for

To show a project's schedule so that everyone can see when each task happens, which tasks overlap, which must wait for others, and whether the project is on time.

Class
Planning (IB teacher support material, p. 26)
Suggested units
Unit 4, Unit 5 (guide, p. 14)

When to use it

  • When planning a project with several tasks and a deadline, such as a launch, a refit or a change programme.
  • When allocating people and equipment, to spot clashes where tasks overlap.
  • When reporting progress to a team, a client or a board.

How to build it

  1. List the tasks and estimate how long each will take.
  2. Identify the dependencies: which tasks cannot start until another has finished.
  3. Draw a time scale along the top and list the tasks down the side.
  4. Draw each task as a bar from its start to its finish, starting each as soon as its dependencies allow.
  5. Mark the milestones, such as a deadline, and shade the bars as work is completed.

The evidence it needs

  • The list of tasks and estimates of their durations, from the people who will do the work.
  • The dependencies between tasks, and the dates of any fixed milestones.
  • When the people and equipment needed are available.

Section 02: What it shows, and what it hides

It reveals
  • The overall schedule and the project's end date, at a glance.
  • Overlaps, where tasks run at the same time and may compete for the same people.
  • Progress against the plan, once the bars are shaded or compared with actual dates.
It does not reveal
  • Which tasks are critical: a critical path network shows that, with each task's float.
  • The cost of the project or the quality of the work.

Limitations

  • Dependencies are harder to read than on a network diagram, especially in large projects.
  • It depends on estimates of duration that may prove wrong.
  • It must be updated as the project changes, or it becomes misleading.

Section 03: Applied: Halden Distribution's thirteen weeks

From the case Halden Distribution.

Source: Simulated data

Drawn as a Gantt chart, the plan in the Halden case lab runs from week 1 to week 13, against the client's deadline in week 14. Listening to the night shift takes week 1; coaching the night team leaders runs from weeks 1 to 6; redesigning the pick routes, weeks 2 to 4; retraining, weeks 5 to 7; the pilot, weeks 8 and 9; the day-shift buddies, weeks 8 to 11; the roll-out, weeks 10 to 12; and the readiness check, week 13.

What it showed

The chart makes the plan easy to share with both shifts: each can see when a change reaches it, and that the pilot and the buddies run side by side in weeks 8 and 9. What it does not show clearly is which tasks have no room to slip. A critical path analysis of the same plan shows that retraining and the pilot have none, while the coaching has three weeks of float.

Read the case file: Halden Distribution

Section 04: In the exam

At HL, the Gantt chart is a toolkit tool for units 4 and 5. Questions may ask for a chart to be constructed from task data or interpreted, or for its usefulness to be compared with critical path analysis. Label the time scale, show the dependencies and the milestones, and comment on what the chart shows about the project's risks.

Common errors

  • Starting a dependent task before the task it depends on has finished.
  • Assuming the project is safe because the last bar ends before the deadline, without checking which tasks have no slack.
  • Leaving out the time scale, its units or the milestone.