Diagram · The business management toolkit · 5.1, 5.6

A critical path network

HL only Fictional figures
A critical path networkA network of six activities between six nodes, each node showing its number, earliest start time and latest finish time. Activity A, 3 weeks, runs from node 1 to node 2; Activity B, 4 weeks, runs from node 2 to node 3; Activity C, 2 weeks, runs from node 2 to node 4; Activity D, 5 weeks, runs from node 3 to node 5; Activity E, 3 weeks, runs from node 4 to node 5; Activity F, 2 weeks, runs from node 5 to node 6. The critical path is A, B, D, F, taking 14 weeks; its activities have no float. Activity C has a total float of 4 weeks and a free float of 0. Activity E has a total float of 4 weeks and a free float of 4.A (3)B (4)C (2)D (5)E (3)F (2)1002333774595121261414NESTLFTNode number, earliest starttime (EST) and latest finishtime (LFT). Durations inweeks, in brackets.Critical path: A → B → D → F, 14 weeksActivity C: total float 9 − 2 − 3 = 4; free float 5 − 2 − 3 = 0Activity E: total float 12 − 3 − 5 = 4; free float 12 − 3 − 5 = 4Critical activities have no float: any delay delays the project.
A critical path networkA network of six activities between six nodes, each node showing its number, earliest start time and latest finish time. Activity A, 3 weeks, runs from node 1 to node 2; Activity B, 4 weeks, runs from node 2 to node 3; Activity C, 2 weeks, runs from node 2 to node 4; Activity D, 5 weeks, runs from node 3 to node 5; Activity E, 3 weeks, runs from node 4 to node 5; Activity F, 2 weeks, runs from node 5 to node 6. The critical path is A, B, D, F, taking 14 weeks; its activities have no float. Activity C has a total float of 4 weeks and a free float of 0. Activity E has a total float of 4 weeks and a free float of 4.A (3)B (4)C (2)D (5)E (3)F (2)1002333774595121261414Critical path: A → B → D → F, 14 weeksC: total float 4, free float 0. E:total float 4, free float 4.In each node: its number, then theearliest start time (top) and thelatest finish time (bottom). Durationsin weeks.

A critical path network HL Earliest start and latest finish times, the critical path, total and free float.
Text description

A network of six activities between six nodes, each node showing its number, earliest start time and latest finish time. Activity A, 3 weeks, runs from node 1 to node 2; Activity B, 4 weeks, runs from node 2 to node 3; Activity C, 2 weeks, runs from node 2 to node 4; Activity D, 5 weeks, runs from node 3 to node 5; Activity E, 3 weeks, runs from node 4 to node 5; Activity F, 2 weeks, runs from node 5 to node 6. The critical path is A, B, D, F, taking 14 weeks; its activities have no float. Activity C has a total float of 4 weeks and a free float of 0. Activity E has a total float of 4 weeks and a free float of 4.

Download SVG