A critical path network HLEarliest start and latest finish times, the critical path, total and free float.Text description
A network of six activities between six nodes, each node showing its number, earliest start time and latest finish time. Activity A, 3 weeks, runs from node 1 to node 2; Activity B, 4 weeks, runs from node 2 to node 3; Activity C, 2 weeks, runs from node 2 to node 4; Activity D, 5 weeks, runs from node 3 to node 5; Activity E, 3 weeks, runs from node 4 to node 5; Activity F, 2 weeks, runs from node 5 to node 6. The critical path is A, B, D, F, taking 14 weeks; its activities have no float. Activity C has a total float of 4 weeks and a free float of 0. Activity E has a total float of 4 weeks and a free float of 4.
Arjun Agrawal | The Business Brief, https://the-business-brief-dun.vercel.app/diagrams/critical-path/. Original teaching material, not an IB publication.
The organizations in the teaching cases are fictional unless a case says otherwise.