Measure or calculation HL only

Net present value (NPV)

Also called NPV

Where you meet this term: IB Diploma

The total present value of an investment's future returns, once each has been discounted, minus the project's original cost, which shows whether the project adds value in today's money.

In plain words

The value today of all the cash an investment will bring in, minus what it costs, so that money arriving later counts for less.

In more depth

NPV = the sum of the present values of the returns − the original cost, each return multiplied by the discount factor for its year at the chosen rate, read from the guide's table for 4%, 6%, 8%, 10% and 20%. A positive NPV means the project earns more than the discount rate; the answer depends heavily on the rate chosen and on the forecast returns.

Formula

Net present value (NPV) = ∑ present values of return − original cost

Work it out in the Financial Laboratory: Net present value (NPV)

In context

A positive NPV means the discounted returns are worth more than the cost, so the project is worth considering, while a negative NPV means it would not earn the rate used for discounting. Unlike payback and ARR, NPV allows for the time value of money, but its result depends heavily on the discount rate chosen and it is harder to calculate and to explain. A discount table is provided in the examination when it is needed.

Example

A fictional bakery considers a $20,000 oven that will return $8,000 a year for three years; at 10% the present values are $7,272.80, $6,611.20 and $6,010.40, so the NPV is −$105.60 and the oven does not pay at that rate.

Common misconceptions

  • Misconception

    A positive NPV guarantees that the project will make a profit.

    In fact

    NPV is only as reliable as the forecast returns and the discount rate; it shows that the project beats the chosen rate if the forecasts prove right.