Bottleneck

Also called Constraint

Where you meet this term: Secondary schoolUndergraduateProfessional

The stage of a process with the lowest capacity, which limits the output of the whole process.

In plain words

The slowest step in a process. However fast the other steps are, the whole process can only go as fast as this one.

In more depth

Output is set by the bottleneck, so an hour lost there is an hour lost for the whole system, while an hour saved elsewhere saves nothing. Bottlenecks show up as queues in front of them and idle time after them. Improvement starts by finding and fully using the bottleneck, then adding to its capacity, after which the constraint moves somewhere else, which is the logic of the theory of constraints.

Example

A fictional sandwich shop can make 120 sandwiches an hour, but its one till serves 60 customers an hour, so at lunchtime the till, not the kitchen, limits its sales.

Common misconceptions

  • Misconception

    Speeding up any step speeds up the whole process.

    In fact

    Only improving the bottleneck raises output; faster steps elsewhere just build bigger queues.