RACI matrix

Also called RACI chart, Responsibility assignment matrix

Where you meet this term: UndergraduateMBAProfessional

A table that sets out, for each task or decision in a project, who is responsible for doing it, who is accountable for it, who must be consulted and who must be informed.

In plain words

A grid that makes clear who does each job, who has the final say, who should be asked first and who just needs to be told.

In more depth

The usual rules are exactly one A for each task and at least one R; too many Cs slow decisions, and too few Is leave people surprised. It clarifies roles in matrix structures, projects and change programmes, where unclear responsibility causes delay and conflict. Some versions add further roles, such as one for those who support the work.

Example

For a fictional café's new branch, the owner is accountable for choosing the site, the operations manager is responsible for the search, the finance officer and the marketing lead are consulted, and the head barista is informed.

Common misconceptions

  • Misconception

    Responsible and accountable mean the same.

    In fact

    The responsible person does the work; the accountable person owns the result and signs it off, and there is only one for each task.